Parkway Railway Station, East Midlands
|
Parkway Railway Station claims to be the greenest railway station in the UK. Work began on East Midlands Parkway in Bristol in December 2007 and finished just over a year later.
IHS was asked by the project engineers to design a heat pump system to supply heating and hot water requirements for the waiting room (approximately 100m²) and staff area (about 60m²). Hot water is required on demand so the system had to be designed accordingly.
Heating and Hot Water System
A 26kW HGL ground source heat pump with 500 litre Hygienik Tank have been installed to ensure constant heat and hot water delivery. Underfloor heating was installed throughout. 1100m² of ground loop pipe was installed into 11 trenches of 50 metres each.